Supporting resort development through infrastructure improvements.
Project Type
Wastewater Treatment
Constructed Value
$16.3 millionDelivery Method
Design-BuildArchitect/Engineer
HDRThe challenge
Expanding infrastructure at the Pala Casino, Spa & Resort required upgrading utility systems that support the resort complex while maintaining operations at an active hospitality destination. Construction activities had to be carefully coordinated so improvements could be completed without interrupting guest services or resort operations. The work also involved integrating new infrastructure with existing utility systems that serve the casino, hotel and surrounding resort facilities.

Awards
DBIA Western Pacific Regional and National Awards of Excellence in the Water/Wastewater Category (under $25 million)
San Diego AGC 2009 Build San Diego Award
highlights
New wastewater treatment facility and lift station retrofit
Four-month environmental clearance delay cut in half
Sustainable elements
Value Engineering reduced project cost by over $1 million
Challenge met
Filanc completed infrastructure improvements that support the casino, spa and resort facilities. The project included upgrades to utility systems and supporting infrastructure that maintain reliable services throughout the property.
Work was carefully coordinated so construction could proceed while the resort remained open and operational. These improvements support continued development of the resort while helping ensure reliable infrastructure for the Pala community and its hospitality operations.