Rehabilitating critical well, storage and pumping infrastructure.

Project Type

Water & Wastewater Infrastructure

Constructed Value
$2,914,554
Delivery Method
Job Order Contract (JOC)
Architect/Engineer
GHD Inc.

The challenge

Rehabilitating infrastructure at the Arrowhead Shores Water Campus required upgrading multiple systems while temporarily shutting down and isolating the facility to complete improvements. The work involved rehabilitating an existing well, improving storage infrastructure and replacing booster pumping systems needed to support water delivery.

Panoramic view of a water storage tank and valve manifold from behind a perimeter wall
highlights

Existing well rehabilitation


Steel tank demolition and rehabilitation


Booster station and controls replacement

Challenge met

Filanc completed the rehabilitation through a Job Order Contract and provided preconstruction services including constructability reviews, cost modeling and value engineering to align the project scope with the City’s budget. The work included rehabilitation of the existing well along with installation of a new well pump and discharge piping.

Additional improvements included demolition of one steel storage tank and rehabilitation of another, replacement of the booster pump station and installation of a new chlorine disinfection system. Filanc also replaced all site electrical and control systems and completed grading, landscaping and irrigation improvements. The upgraded infrastructure supports long-term operations and strengthens the City of Peoria’s water system.

Recent Projects

Morrow Bay Water Treatment Facility

Morro Bay Water Reclamation Facility

Facility for Agriculture

MF/RO Facility for Agriculture

Santa Margarita Conjunctive Use Project Facilities